Working plans

Introduction

Department has a working plan wing headed by Additional Principal Chief Conservator of Forest, at Gandhinagar. There are three regional working plan circles at Junagadh, Surat and Vadodara headed by ccf/cf rank officers. Working Plan wing has also developed a state of art G.I.S. and Remote Sensing Center at Vadodara for creating Geo-spatial inventories of forest resources, thematic maps and change detection of forest cover of different divisions required for planing of forest management.

Forestry management in India as well as in Gujarat has passed through various phases. The National Forest Policy of 1988 has recognized the importance of managing our forests on Silvicultural principles commensurate with the Societal and Environmental concerns. It also mentions that no forest be permitted to work without the government approved management plan in a prescribed format. para 4.3.2 of the national forest policy clearly states :

“No forest should be permitted to be worked without the government having approved the management plan, which should be in a prescribed format and in keeping with the national forest policy. The central government should issue necessary guidelines to the state governments in this regard and monitor compliance.”

According to National working plan code, working plan is a tool for scientific forest management. It is very useful for evaluating the status of forest resource of a division, assessing the impact of past management practices and deciding about suitable management interventions for future. periodical up-dating and revision of working plans is essential to keep pace with the trends emerging out of forest–people interface and to address other national and international obligations. the preparation of working plan is a highly technical and time-framed scheduled operation. the preparation of the working plan is based on stock maps which is prepared through ground surveys. Recently, the use of modern tools like remote sensing, G.I.S. & GPS is being done for preparing the forest cover maps of divisions. Every working plan includes the area-specific scientific prescriptions for proper management of forests of a particular forest division. Accordingly, the working circles, felling series, and annual coupe area computations are done for the plan period for implementation of the working plan prescriptions.

Status Of Working Plans in Gujarat State.

Gujarat state is situated along the western coast of the country with a total geographical area of 19145.83 sq km having only 9.8% designated forest lands, divided by the tropic of cancer. The forests of gujarat consist of four major types, namely (1) tropical moist deciduous, (2) tropical dry deciduous, (3) littoral and swamp and (4) northern tropical thorny forests. Most of the forest area is confined mainly in the districts of Valsad, Dangs, Vyara, Rajpipla, Chhotaudepur, Baria, Godhra, Sabarkantha, Banaskantha, Junagadh and Kachchh. Mangrove forests are mainly found in Jamnagar and Kachchh districts.

For forestry management purpose, the forests of the state are divided into 22 territorial forest divisions and 2 forest sub-divisions and these are covered under 17 approved working plans (as shown in the Statement). Total forest area covered under the management of working plans 17,09,294 ha. the area covered under the working plans are less than the actual forest area of the state because rest of the area are covered under management plans of sanctuaries and national parks. all of these working plans have basically been formulated for improving Conservation and Development of Forest Resources of the State. Clear-felling of forest area is not included in any of these plans. much higher emphasis has been given to conservation, people’s involvement for regeneration of forests, increasing the NTFP outputs, Bio-diversity Conservation, medicinal plants, etc. The working plans are supported by different ongoing research projects like forest resource survey, Socio-Economic studies, regeneration studies and specific studies on seeds, seedlings etc.

Sr. no.

Name of working plan

Prepared by

Period

Yrs

From - to

No of div .

Name of divisions

Remarks

1

Dangs

Anoop Shukla IFS

15

1997-1998 to 2012-2013

1

Dangs north

Approval letter no(GOI) 12-7/92(FOR)/2135

Dt:25-07-1997

Extension for one year i.e 2013-14 sanctioned vide GOI  letter no:12-7/92 (for)1772 dt:07-11-2012

Extension for further one year i.e 2014-15 sanctioned vide GOI  letter no:12-7/92 (FOR)609 Dt:10-03-2014

Review and Extension proposal of Existing working plan of Dang forest division is approved in State level committee meeting Dated :12-09-2014

2

Dangs south

2

Vyara

A.K.Verma IFS

20

1999-2000 to 2018-2019

3

Vyara

Approval letter no (GOI) 2-58/99(FOR)/586

Dt:30-03-1999

3

Rajpipla

Dr Jaipal Singh IFS

10

2005-2006 to 2014-2015

4

Narmada

Approval letter no (GOI) 12-4/2002(FOR)/1366,

Dt:14-07-2012

FPWPR is approved in State level committee meeting Dated :11-09-2014

5

Surat

6

Bharuch sub-division

4

Chhotaudepur

Rakesh Agrawal IFS

10

2003- 04 to 2012-2013

7

Chhotaudepur

Approval letter no (GOI)

12-6/92(FOR)/46, dt:06-01-2004

Extension for one year i.e 2013-14 sanctioned vide goi  letter no:12-6/92 (for)1517 dt:17-09-2012

Extension for further one year i.e 2014-15 sanctioned vide GOI  letter no:12-6/92 (FOR)546 Dt:28-02-2014

Final Draft Working Plan of Chhotaudepur Forest Division is approved in State level committee meeting Dated :12-09-2014.

5

Panchmahals & kheda

S.N. Tyagi IFS

10

2008-2009 to 2017-2018

8

Godhra

Approval letter no (GOI)

12-6/2002(FOR)/78 dt:05-01-2009

9

Nadiad s.f

6

Gandhinagar

R.D.Kamboj IFS

10

2002-2003 to 2011-2012

10

Gandhinagar

Approval letter no (GOI)

12-1/2002(FOR)3457,

Dt:09-10-2002

Extension for one year i.e 2012-13 sanctioned vide GOI letter no:12-1/2002 (FOR)1558 dt:17-09-2012 further 1 year extension

(up to 2013-14) (GOI) letter no.12-1/2002(FOR)1609, Dt.4-10-2013

7

Sabarkantha

A.P.Singh IFS

10

2003-2004 to 2012-2013

11

Sabarkantha (north)

Approval letter no (GOI) 12-1/2000(FOR)2617

Dt:25-11-2003

Extension for one year i.e. 2013-14 sanctioned vide (GOI) letter no:12-1/2000 (FOR)/1516 dt:17-09-2012

Extension for further one year i.e 2014-15 sanctioned vide GOI  letter no:12-1/2000 (FOR)/545 Dt:28-02-2014

12

Sabarkantha (south)

8

Banaskantha

Dr.A.K.Varshney IFS

10

2004-2005 to 2013-2014

13

Banaskantha

Approval letter no (GOI) 12-37/97(FOR)/745

Dt:22-04-2004.

Extension for one year i.e 2014-15 sanctioned vide GOI letter no:12-37/97(FOR)/325, Dt:18-02-2014 for Banaskantha Forest Division.

FPWPR of Patan Forest Division is approved in State level committee meeting Dated :11-09-2014.

14

Patan division

9

Junagadh

M.V.Parmar IFS

10

2004-2005 to 2013-2014

15

Junagadh

Approval letter no (GOI) 12-1/2003(FOR)/1554

Dt:12-08-2004

Extension for one year i.e 2014-15 sanctioned vide GOI letter no:12-1/2003(FOR)/267, Dt:12-02-2014 for Junagadh Forest Division.

FPWPR  of Porbandar Forest Division is approved in State level committee meeting Dated:11-09-2014.

16

Porbandar division

10

Bhavnagar

R.D.Kamboj IFS

10

2002-2003 to 2011-2012

17

Bhavnagar

Approval letter no (GOI) 1 2-3/2002(FOR)/2475 Dt:11-10-2002

Extension for one year i.e. 2012-13 sanctioned vide GOI letter no:12-3/2002 (for)1067 dt:03-07-2012

Further 1 year extension(up to 2013-14) GOI letter No.12-3/2002(for) 1610, dt.4-10-2013

Final Draft Working Plan is approved in State level committee meeting Dated :12-09-2014.

18

Ahmedabad

S.F

11

Jamnagar

Dr.Sanjeev Tyagi IFS

10

2012-2013 to2021-2022

19

Jamnagar

Approval letter No.(GOI) 12-1/2006(FOR)1139

Dt:13-07-2012

12

Rajkot

Dr.Sanjeev Tyagi IFS

10

2012-2013 to 2021-2022

20

Rajkot

Approval letter no (GOI) 12-9/2012(FOR)1606

Dt:10-10-2012

13

Surendranagar

R.K.Sugoor IFS

10

2004-2005 to 2013-2014

21

Surendranagar

Approval letter no (GOI) 12-2/2002(FOR)/1551 dt:11-08-2004

Extension for one year i.e 2014-15 sanctioned vide GOI letter no:12-2/2002(FOR)/320, Dt:18-02-2014 for Surendranagar Forest Division.

FPWPR is approved in State level committee meeting Dated :11-09-2014.

14

Kutch

D.B.Ande IFS

10

2003-2004 to 2012-2013

22

Kutch East

Approval letter no (GOI) 12-38/97(FOR)/176

Dt:27-01-2004

FPWPR is received. suggested for inclusion of certain points in revised FPWPR.

Extension for one year i.e. 2013-14 sanctioned vide (GOI) letter no:12-38/97 (for)1611 dt: 04-10-2013

Extension for further one year i.e 2014-15 sanctioned vide GOI  letter no:12-38/97/ (FOR) / 321, Dt:18-02-2014

FPWPR is approved in State level committee meeting Dated :11-09-2014.

23

Kutch West

15

Valsad

U.D.Singh IFS

10

2004-2005 to 2013-2014

24

Valsad South

Approval letter no (GOI) 12-2/2000(FOR)/740

Dt:22-04-2004

Extension for one year i.e 2014-15 sanctioned vide GOI  letter no:12-2/2000/ (FOR) / 319, Dt:18-02-2014

FPWPR is approved in State level committee meeting Dated :11-09-2014.

25

Valsad North

16

Dahod

S.N. Tyagi IFS

10

2008-2009 to 2017-2018

26

Baria

Approval letter no (GOI)

12-7/2008(FOR)/116

Dt:12-01-2009

17

Banni protected forest

S. C. Srivastav IFS

10

2009-2010 to 2019-2020

27

Banni Grassland division

Approval letter no (GOI)

12-8/2009(FOR)/72

Dt:11-01-2010

Grassland, Kutch